An AI forecasting platform for a weather agency

NVIDIATechnical presentation60 minutes

15 monthsto go live

Format reported for NVIDIA Solutions Architect interviews (5 independent sources, latest November 2026). Our case is original.

The prompt

Your brief, sent 5 days before the interview. Prepare a 30-minute presentation of the AI infrastructure you would propose, with 7 to 12 slides. A panel will interrupt with questions. Then 30 minutes of open questions.

Calder Meteorological Agency (fictional) is a national weather service.

Business facts:

  1. It runs physics-based forecasts on a CPU supercomputer managed with Slurm, 4 forecast cycles a day.
  2. It wants an AI forecast model in daily operations for the next storm season: live in 15 months.
  3. Budget: €14 million of capital over 2 years, including 3 years of support. Everything stays on premises in the country, because this is an emergency service.
  4. Team: 6 HPC engineers who know Slurm, a parallel file system and InfiniBand from the CPU system, and 4 ML researchers. Nobody has run Kubernetes.
  5. Forecasts feed the civil-protection alert service. A late forecast cycle counts as a public-safety incident.

Technical numbers from the agency:

  1. One full training run of their model took 110,000 H100 GPU-hours on a rented prototype. They plan 4 retrains a year, plus experiments worth 2 more full runs: 6 runs a year. A full run must finish within 4 weeks.
  2. Training data: 210 TB after preprocessing. A run reads it 12 times, in random order.
  3. Each forecast cycle runs 50 ensemble members. A member is 40 steps of 6 hours (10 days ahead), and each step takes 1.1 s on one H100. The whole ensemble must finish within 20 minutes of the input data arriving.
  4. Output: 2.6 GB per member per step. Keep 30 days of output online.
  5. Facility: 14 free rack positions, air-cooled, up to 25 kW per rack. Power is not a limit.

Assume:

  • An 8-GPU H100 node costs €300,000 with 3 years of support and draws up to 10.2 kW.
  • The InfiniBand fabric costs €35,000 per node. Parallel storage costs €800 per usable TB.
  • Two of the 14 rack positions go to network and storage.
  • Electricity costs €0.18 per kWh, with a PUE of 1.35. Nodes average 70% of their peak draw.

Your answer

Before you make any slide, write the one sentence the agency's director should remember, and the five numbers that go on your sizing slide.

Compare your answer

A weak, a good and a great answer, side by side, then the guide, the follow-ups and the rubric.